Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the the-events-calendar domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the broken-link-checker domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the woocommerce-eu-vat-number domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114
Finger injury while using a crowbar to try to shift a large shackle - DEV imca
Skip to content

Finger injury while using a crowbar to try to shift a large shackle

What happened?

During anchor handling operations, one anchor was on deck and crew were required to connect a wire socket to the anchor by using a shackle. The wire socket was in a difficult position for the shackle to be connected; to overcome this difficulty, the deck crew used a crowbar to try to get these items aligned. The crowbar eventually slipped while it was in use for the shackle’s pin connection and consequently a crew member suffered an injury to the right ring finger.

The injured person received first aid treatment on board. He was subsequently sent to a barge to be checked by an available medic. The recommendation of the medic was that he be sent to hospital ashore.

What went wrong? What were the causes?

Similar incidents involving connection/disconnection of shackles are known to the industry, and have often led to serious injury. Causes identified include inadequate identification of pinch points, and improper use of tools.

Lessons learnt

  • Hazards can be hidden and risky situations may not always be identified;
  • All crew members involved in similar tasks should be aware that use of crowbars on rigging under tension is not safe. Capstans or tugger winches should be used to reposition chains, wires or anchors. Only after everything is safe and without residual tension should the rigging team perform manual work;
  • Another point to remember: never place your hand (or any part of your body) ‘in the line of fire’.

This is a recent incident and is still under investigation. Any additional lessons learnt identified will be communicated following the investigation completion.

Members may wish to refer to the following incident:

  • Lost time injury (LTI): Gangway deployment

    A crowbar was used to exert pressure on the lower section of the gangway, to allow the outboard pin to be removed. During this process, both the bosun and the AB were standing within the steps of the gangway when an outboard pin jumped out this section slid up quickly and trapped the bosun and able seaman. This extremely serious incident could have been avoided entirely by following the correct procedures.

Safety Event

Published: 21 December 2017
Download: IMCA SF 32/17

Relevant life-saving rules:
IMCA Safety Flashes
Submit a Report

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding safetyreports@imca-int.com to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.

IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.

IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.