Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the the-events-calendar domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the broken-link-checker domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the woocommerce-eu-vat-number domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114
Near miss: uncontrolled movement of gangway - DEV imca
Skip to content

Near miss: uncontrolled movement of gangway

What happened?

A vessel gangway moved in an unplanned way and could have been lost overboard.  The incident occurred when the starboard gangway was under maintenance; the upper part of the turning platform had been removed earlier for maintenance.  As a result, the gangway ladder was not connected to the turning platform.  The ladder was secured with bolts.

In order to repair a corroded part of the fixed gangway platform, a welder secured the forward part of the gangway with rope.  Then he loosened the securing bolts and gave a little slack on the gangway wire. 

At that moment, the forward rope slipped off and the forward tip of gangway fell 2-3m from where it was secured.  The aft tip of the gangway ladder was hanging by the gangway wire and securing rope.  The forward part of the ladder was approx. 2-3m lower.  The gangway wire and securing ropes on the aft part prevented the gangway from further falling over to the side.

Other crew immediately brought chain blocks and other equipment to secure and recover gangway ladder back in to the place.

What went wrong?

What ought to have been simple, straightforward and safe maintenance turned into a near miss.  Two crew members were busy with the task and neither of them thought that anything could go wrong.

What was the cause?

  • Human error:
    • inadequate attention to detail
    • inadequate job preparation
    • inadequate supervision.

What lessons were learned?

  • Reiterate the importance of safety awareness at the highest level with each and every job – the lesson is that things can go wrong with the most straightforward and ‘routine’ jobs. Complacency is to be guarded against.

Members may wish to refer to:

Safety Event

Published: 1 July 2019
Download: IMCA SF 15/19

Relevant life-saving rules:
IMCA Safety Flashes
Submit a Report

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding safetyreports@imca-int.com to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.

IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.

IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.