Skip to content

Near-miss (HIPO): Engine started and running whilst crew member working on shaft generator

A member has reported an incident in which an engine and shaft generator started running whilst a crew member was working on it. The incident occurred during planned monthly maintenance on carbon brushes on a propeller shaft located inside the pedestal underneath the generator. Whilst the crew member was performing his task, the duty engineer received an order from the bridge to start the port side main engine. The crew member was located inside the pedestal underneath the generator when the propeller shaft was clutched in and started rotating. He managed to escape from the area and reported the incident to engine control room (ECR) personnel.

There were no injuries, but this was a high potential incident with the possibility of a fatality or of life threatening injuries resulting in permanent disability.

An investigation revealed the following: . The isolation (‘lock out/tag out’) system was not sufficient for this work on the generators. The port side main engine was in standby mode and there was no isolation to the system before starting the ‘routine’ maintenance on the shaft; . There was inadequate supervision. The crew member started the job unsupervised, and there was only limited confirmation from the crew member that he understood what the job entailed; . There was incomplete understanding of how to approach a task of this sort safely, in terms of toolbox talks, permits to work and ‘stop work authority’; . There was an unplanned change which was not properly managed. It had not been planned to turn the vessel when the electrician reviewed this planned or required maintenance work, and then when the decision was taken to turn the vessel, the electrician was not informed; . There was a lack of communication during several phases of operation:

  • engine control room (ECR) personnel and bridge personnel were not informed about maintenance on the generator
  • the electrician was not informed of a planned turning of the vessel when preparing these tasks
  • vessel personnel did not report the incident in timely manner – the onshore organisation was not informed until 24 hours after the incident;
  • There was insufficient knowledge of permit to work (PTW), isolations and barriers, and risk assessment requirements;
  • There was a serious lack of compliance with existing company procedures:
    • the pre-job conversation between supervisor and crew member was not in compliance with company requirements and procedures
    • this was the third time the crew member had performed this task, and there was no PTW or isolation certificate completed on this occasion
    • the opposite shift had also performed this task and had not used a PTW either, although there was a signboard in the ECR stating that work on equipment was in progress.

The following causes were identified:

  • Immediate causes:
    • bridge and ECR not informed regarding on-going work on shaft generator
    • port main engine in standby mode after unmanned engine room test;
  • Underlying causes:
    • PTW and isolation certificate not issued
    • risk assessment not followed
    • failure to inform ECR on planned maintenance
    • lack of robust communication routines;
  • Root causes:
    • lack of safety awareness
    • lack of management control.

The following lessons were learnt:

  • The necessity for a PTW and isolation of equipment should have been identified. This would have ensured proper isolation of equipment, ensured that bridge and ECR personnel were informed of on-going work, and ensured the crew member could complete the task with all safety precautions/barriers in place;
  • All employees have the authority and obligation to stop any task or operation where there are concerns or questions regarding the control of safety, health and environment;
  • Improved incident reporting routines should be established to ensure that shore management is notified accordingly and to ensure that there is an appropriate ‘safety time out’ following incidents.

The following actions were taken immediately:

  • Time out for safety held to discuss the incident, with focus on PTW, awareness and communication;
  • Planned maintenance procedures updated with requirements for PTW and isolation of shaft generator;
  • Sign made and posted on generator informing of lock tag requirements;
  • Fleet-wide communication and discussion of incident.

The following further recommendations were made:

  • Improvements should be made to toolbox talks and risk assessment for ‘routine’ jobs, particularly with reference to isolations and barriers;
  • Better pre-shift meetings in engine department should ensure good planning and identification of simultaneous activities;
  • ‘Stop work authority’ and behaviour based safety programmes should be reinforced.

Members may wish to refer to the following similar incidents (search words: spinning, rotating)

Safety Event

Published: 28 August 2015
Download: IMCA SF 12/15

IMCA Safety Flashes
Submit a Report

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding [email protected] to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.

IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.

IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.