Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the the-events-calendar domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the broken-link-checker domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the woocommerce-eu-vat-number domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114
Near-miss: Dropped object: 6kg sledge hammer head - DEV imca
Skip to content

Near-miss: Dropped object: 6kg sledge hammer head

A member has reported an incident in which a 6kg hammer head fell 5m (metre) to an unmanned deck. Whilst using the sledge hammer to dislodge a 600Te shackle connecting a 340Te wire, the hammer head came free of the wooden shaft when it was struck against the shackle pin, and it fell 5m to the unmanned area below which had no barriers in place. There were no injuries.

On closer inspection, it was noted that there were a number of small indentations around the head and along the shaft, two hairline cracks at the head end of the hammer and a large open split at the user end of the handle. It was also noted that the lanyard used to secure the handle was an inadequate solution for the retention of tools used at height.

Closer inspection of handle and hammer head
Closer inspection of handle and hammer head

Following investigation, it was identified that there had been numerous other occasions where hammer heads had either been found loose or had come off during use. In addition, several cases reported damaged shafts.

The following lessons were learnt:

  • The inspection for damage of all hand tools should always be carried out prior to use and before returning to storage location;
  • Hammer heads should be checked for security prior to use, ensuring heads are securely fixed to handle;
  • Defective tooling should be removed from service and quarantined;
  • Appropriate tool retention methods should be used when working at height with tools; different methods may be appropriate for tools of different weight;
  • The tool lanyard connection point should either be supplied with the hammer, recommended by the tool manufacturer or be a recommended and approved lanyard manufacturer’s modification.
Some suggested tool lanyard arrangements
Some suggested tool lanyard arrangements

Safety Event

Published: 1 November 2011
Download: IMCA SF 12/11

IMCA Safety Flashes
Submit a Report

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding safetyreports@imca-int.com to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.

IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.

IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.