Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the the-events-calendar domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the broken-link-checker domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the woocommerce-eu-vat-number domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114
Hammer dropped from height - DEV imca
Skip to content

Hammer dropped from height

IMCA has received details of an accident wherein a tool was lost from work at height and fell 6-7 metres to a walkway. No-one was injured.

Work was ongoing to remove an obsolete bracket from a derrick beam. A 1.6 kg hammer in use came loose from its double sealed spring hook and fell 6-7 metres to a walkway below, which at the time of incident was completely sealed off. The hammer, safety wire and two double sealed spring hooks were all tools dedicated and solely used for work in height.

The resulting investigation identified the following direct cause:

  • The finger articulation on the carbine hook was riveted to the spring hook body. However. the spring hook was found to be without this rivet. It might have slid out during the work due to incorrect riveting or the rivet might have been broken in two pieces during the work. The spring hook itself was not deformed or damaged in any way.

and the following contributory factors:

  • The spring hook (length = 54 mm, bow diameter = 25 mm, t = 5mm) is made of solid stainless steel.
  • The spring hook was designed for tension along its longitudinal axis and not for loads directly on its locking mechanism.

The company recommended the following immediate actions:

  • All similar spring hooks have been taken out of use
  • Spring hooks have been temporarily replaced with shackles with split pins

plus the following preventive measures:

  • The spring hooks are to be replaced with a better quality double seal type
  • The vendor has been informed of the incident
  • Relevant findings from the investigation are being distributed appropriately.

Safety Event

Published: 31 January 2006
Download: IMCA SF 01/06

IMCA Safety Flashes
Submit a Report

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding safetyreports@imca-int.com to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.

IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.

IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.