Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the the-events-calendar domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the broken-link-checker domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the woocommerce-eu-vat-number domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/storm/sites/dev-imca-int-com-1/public/wp-includes/functions.php on line 6114
Fatality: Falling object - DEV imca
Skip to content

Fatality: Falling object

A member has advised of a fatality, the initial details of which follow.

During wireline toolstring recovery, accidental contact with the wireline sheave was made, causing the assembly to fall to deck, fatally injuring a crew member. This occurred when the port pod line was raised to allow visual inspection of the bottom of toolstring and to break tool down without wireline being paid out first.

The company has noted the following lessons to be learnt:

  • The common industry practice of working in close vicinity to suspended wireline tools presents a dropped object hazard that should be recognised and eliminated; . Communications between all team members involved with lifting operations needs to be improved; . In lifting operations, all necessary steps should be taken to ensure that tools/devices are not drawn into any sheave; . Risk assessments of wireline lifting operations must identify such hazards; . Written work procedures must clearly state how risks will be managed; . Common work practices and contingency activities must be subject to risk assessment and documented as a written procedure.

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding safetyreports@imca-int.com to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.

IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.

IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.